SURVIVABILITY REPORT

« Back to front page

Compartment R.DB04P

Properties

Description:Day Tank
Purpose:DO
Volume:1.6 m³
Vessel: PATROLBOAT

Location of the compartment in the vessel and the EBPs surrounding the compartment:

EBPs

The following EBPs are located in this compartment:

NameAdjacent compartmentOrientationAreaPlate thicknessPlate materialPlate massStiffener materialMass from stiffenersTotal EBP massCoG XCoG YCoG ZBallistic protection IDBallistic protection thickness
EBP.R.DB03C.19 R.DB03C X0.76 m²5.0 mmA29.85 kgA4.83 kg34.67 kg9.60 m0.62 m1.21 mMST5.0 mm
EBP.R.DB03C.21 R.DB03C X1.04 m²5.0 mmA40.67 kgA6.88 kg47.55 kg11.40 m0.63 m1.10 mMST5.0 mm
EBP.R.DB03C.23 R.DB03C Y1.06 m²5.0 mmA41.64 kgA48.60 kg90.23 kg10.55 m1.30 m1.20 mMST5.0 mm
EBP.R.DB03C.25 R.DB03C Z2.34 m²5.0 mmA91.84 kgA42.42 kg134.27 kg10.50 m0.65 m1.50 mMST5.0 mm
EBP.R.DB04P.3 R.DB04S Y1.34 m²5.0 mmA52.54 kgA61.32 kg113.87 kg10.54 m0.00 m1.13 mMST5.0 mm
EBP.R.DB04P.6 OUTSIDE Z2.38 m²6.3 mmA117.63 kgA108.96 kg226.59 kg10.50 m0.65 m0.81 mMST6.3 mm

More information about Materials and Structures.

Equipment

The following equipment is located in this compartment:

IDEquipment tableDescription
DO5 EQP*DODiesel oil day tank ENG1

Detonation

Detonation does not take place in this compartment in any of the cases.

Damage

The probability that this compartment gets damaged is 15.93 %.

It's damaged in the following cases:

#NameProbabilityCauseWarhead
2 EXOCET-RDB03C 15.32 %Pressure, fragmentation, flooding EXOCET
25 EXOCET-RDM02P 0.61 %Pressure EXOCET

© 2017 Surma Ltd